1.0              Purpose

The purpose of this SOP is to lay down operational procedure of Disintegration test Apparatus.

2.0              Scope

This procedure is applicable to Quality Control and Quality Assurance Department.

3.0              Responsibility

Officer QC/QA

Asst. Manager QC/QA

Manager QC/QA

4.0              Accountability

Manager QA

5.0              Terms and Definitions

N/A

6.0              Precautions

6.1              Check all the connections and circuits before use

6.2              Wear mask and gloves while operating the instrument.

6.3              Avoid excessive force during removing and placing of basket rack assembly.

6.4              Check water level in the tank before switching “ON” the apparatus.

6.5              Avoid abrasive material while cleaning the instrument.

7.0                 Reference

N/A

8.0              Procedure

8.1              Ensure that the instrument and area is properly clean.

8.2              Use DI water in water bath.

8.3              Fill the beaker with purified water or other medium if required up to the desired volume.

8.4              Turn “ON” the main power.

8.5              Turn “ON” the heater by pressing the temperature button.

8.6              Check that is the temperature reached the desired temperature i.e 37 oC ± 2.

8.7              Set the time as per the test requirement using arrow key of time.

8.8       Place one tablet/capsule in each of the six tubes of basket rack assembly and place disk if   required.

8.9              Turn “ON/OFF” key to start the oscillation smoothly at constant frequency

8.10          Watch the tablets/capsules till their complete disintegration.

8.11          Use “ON/OFF” button to stop the oscillation.

8.12          Make entry in DT apparatus log book.

8.13          To pass the test all the tablet/capsule must have disintegrated within specified time.

9.0              Abbreviations

9.1          SOP     Standard Operating Procedure

9.2              QC       Quality Control

9.3              QA       Quality Assurance

9.4              DI         Deionized

9.5              DT        Disintegration Test

10.0          Annexure

N.A